Establishment of CP department in GCC Co. including manpower, tools, materials &
equipment that helped in making more profit to company.
Complete construction CP of more than 100 wells oil & gas and related flow lines
approved by ARAMCO.
Complete construction and pre commissioning CP of:
• 25Km, 16” DM3FG-1 gas pipeline.
• 35KM, 24” FZRN trunk line.
• 13KM, 42” WIP-1 water pipeline.
• 45 KM, 10” KHZM water pipeline.
• 40 KM, 12” DYBN water pipeline.